Rebuilding the Brazos River Bridge

r_i_straw Jun 8, 2016

  1. r_i_straw

    r_i_straw Mostly N Scale Staff Member

    22,280
    50,211
    253
    image.jpeg
     
    rch likes this.
  2. r_i_straw

    r_i_straw Mostly N Scale Staff Member

    22,280
    50,211
    253
    image.jpeg
     
    rch and BoxcabE50 like this.
  3. Hytec

    Hytec TrainBoard Member

    13,976
    6,938
    183
    Fantastic repair, and completed before the Brazos has fully recovered. There must be a building full of repair plans for every possible catastrophe. Just a matter for a team to inspect the site, select the correct plan, assemble staff, contractors, vendors, material, and logistics, and finally go to work.....WOW :eek:

    Russell, thank you for your excellent coverage. (y)
     
  4. BoxcabE50

    BoxcabE50 HOn30 & N Scales Staff Member TrainBoard Supporter

    67,640
    23,049
    653
    These guys are good! This is how projects should be done. Now I am hoping someone may be nearby to catch the first train across.
     
  5. RBrodzinsky

    RBrodzinsky November 18, 2022 Staff Member TrainBoard Supporter In Memoriam

    5,685
    2,786
    98
    Do you think there will be future work to put a more substantial pier in place? Is the girder even connected to the two new piers, or is it just resting on them, with the bridge resting on it?

    (Yeah, some of my questions may be due to being from earthquake country -- and not being a civil/structural engineer)
     
  6. BoxcabE50

    BoxcabE50 HOn30 & N Scales Staff Member TrainBoard Supporter

    67,640
    23,049
    653
    With regard to Rick's question, as I recall, railroad bridge shoes float on the cap? Due to expansion/contraction?
     
  7. Mr. SP

    Mr. SP Passed away August 5, 2016 In Memoriam

    1,801
    928
    35
    After all the repairs are done they should get the painting gang out there and paint the rusty bridge.
     
  8. r_i_straw

    r_i_straw Mostly N Scale Staff Member

    22,280
    50,211
    253
    I hung around for 2 hours but no trains. Saw a couple of high railers go over.
     
  9. BoxcabE50

    BoxcabE50 HOn30 & N Scales Staff Member TrainBoard Supporter

    67,640
    23,049
    653
    Now they need to stabilize that river bank and protect the exposed pilings.
     
  10. gjslsffan

    gjslsffan Staff Member

    2,634
    5,760
    69
    Typical UP. Here UP DS say they dispatch more MW than trains lol. Should not compare here to there, but. Prolly crews are either, furloughed, DOL or LOS (Lay off sick). I never seen the like in my RR career. Great thread though.
     
  11. r_i_straw

    r_i_straw Mostly N Scale Staff Member

    22,280
    50,211
    253
    image.jpeg One of the MOW high railer trucks leaving the tracks after crossing the bridge.
     
  12. r_i_straw

    r_i_straw Mostly N Scale Staff Member

    22,280
    50,211
    253
    Well, I guess it is all cleanup and bank stabilization from here on out. The river is not going to go down very fast. They are dumping huge amounts of water from reservoirs in North Texas on the west side of Fort Worth. I crossed the river between Milam and Robertson Counties this afternoon and it is quite high there yet. Here is a photo of the new pier taken while I was waiting for the "first train" on Wednesday. I guess it finally came but I was on the road by then.
    DSC_0005.jpg
     
    hoyden likes this.
  13. Traindork

    Traindork TrainBoard Member

    1,299
    393
    35
    Trains are rolling. I saw a total of 5 trains from Post Oak to Richmond, about 20 miles worth of track.
     
  14. Traindork

    Traindork TrainBoard Member

    1,299
    393
    35
    ... and now the rumor is that the bridge is still sinking and will be replaced and should take about 18 months.
     
  15. BoxcabE50

    BoxcabE50 HOn30 & N Scales Staff Member TrainBoard Supporter

    67,640
    23,049
    653
    If still sinking, it will require some interesting engineering to stop that problem. I'm going to be interested in seeing project!
     
    gjslsffan likes this.
  16. Hytec

    Hytec TrainBoard Member

    13,976
    6,938
    183
    They may have to consider a truss or cantilever design supported by massive concrete abutments if they can't get enough adhesion for bents.

    NASA had the same problem when the Saturn engine test stands were built at the Mississippi Test Facility. The original design called for 2500 200' piles to support the stand. When the first pile was hit, it immediately shot out of sight like an arrow into Devil's Swamp mud. They ended up having to use 500' piles to get enough adhesion. Apparently nobody noticed that the core samples had been obtained from 3/4 mile away......:rolleyes:
     
  17. Traindork

    Traindork TrainBoard Member

    1,299
    393
    35
    The bridge will be out of service for two weeks, don't know if they started or not. I'm guessing they're going to try and do another patch before they have to spend a lot of money. UP is a very cheap company. :whistle:
     
  18. BoxcabE50

    BoxcabE50 HOn30 & N Scales Staff Member TrainBoard Supporter

    67,640
    23,049
    653
    Hoping to see more progress photos...
     
  19. r_i_straw

    r_i_straw Mostly N Scale Staff Member

    22,280
    50,211
    253
    The next pier out has been shifting. Not as severe as the first one but I guess they are gun shy.
    DSC_0009.jpg
    Can't detect much from this angle.
    DSC_0002.jpg
    Using a barge, they have set three piles on the west bank and mounted huge cable winches on top of them.
    DSC_0008.jpg
    I guess they are going to work this next job from barges secured by these winches. They were starting to set more of them on the east bank while I watched.
    DSC_0003.jpg
     
    Last edited: Jul 7, 2016
    hoyden likes this.
  20. Hytec

    Hytec TrainBoard Member

    13,976
    6,938
    183
    Build on the Cheap, and pay Double later for what it would have cost to do it right originally. Been There, Done That, Got Lotsa Coffee Cups. :(
     