    I didn’t accomplish as much as I wanted to over the extended holiday weekend, but progress is progress.

    SD35 #2800 is completed and operational on the layout, RS3 #6225 is also complete but needs a decoder. SD35 #2803 is ready for reassembly as soon as the front number boards are lettered.
    [​IMG]
    [​IMG]



    I also finished roughing in the basic land forms around the north end of the lower level tunnel through the hallway corner. I have a few ideas for this area that may or may not involve a dirt road and a Mail Pouch barn.
    [​IMG]


    Finally, between locomotive work, I did wrap up some old freight car projects. Another woodchip hopper is ready for service and a few other cars that had been on the rip track for a couple of years were finally serviced and released from the car shop.
    [​IMG]


    Sent from my iPhone using Tapatalk
     
  2. thetramp

    thetramp TrainBoard Member

    329
    433
    17
    What do you use as the base for the mountains?
     
  3. GP30

    GP30 TrainBoard Member

    3,423
    1,819
    71
    Insulation foam board, either 1 or 2 inch. Works well for planting trees later.


    Sent from my iPhone using Tapatalk
     
    Uncle peanut butter likes this.
  4. GP30

    GP30 TrainBoard Member

    3,423
    1,819
    71
    Un-sexy Sunday…. Is there a hashtag for that?

    Anyhow, the subroadbed for both main tracks north and south of Grantsville have tunneled through the same hallway corner directly above the tunnel shown on the last update.
    [​IMG]


    While waiting for glue to dry on the plywood and risers, I assembled a Bowser 2 bay hopper. GE had a large light bulb factory near Youngstown, Ohio that made their Mazda bulbs. I can use several more of these ILDX hoppers for hauling sand from a quarry at Grantsville to GE factories.
    [​IMG]


    That’s it for this weekend, hopefully I can get more track laid down on the upper level in the next 2-3 weeks. It ain’t sexy, but it’s something!


    Sent from my iPhone using Tapatalk
     
    Joe Lovett, Moose2013 and BoxcabE50 like this.
  5. VinceP

    VinceP TrainBoard Member

    1,624
    1,348
    35
    Love the units looking great
    And progress is progress
     
  6. GP30

    GP30 TrainBoard Member

    3,423
    1,819
    71
    Begin Double Track

    The turnouts for the north end of Spencer have been built over the previous holiday weekend. It consists of a #8 crossover for the north end of the double track between Spencer and Elkview on the upper level. The left hand #6 turnout will connect to the Spencer yard lead and passing track. The #8 to the right will be Main #2 (we would be looking south in this arrangement) and a short branch to a small coal loading operation at Millstone.

    This weekend was mostly general basement finishing work and clean up for the special blitz week July 17-20.[​IMG]


    Sent from my iPhone using Tapatalk
     
    Joe Lovett, BNSF FAN and BoxcabE50 like this.
  7. GP30

    GP30 TrainBoard Member

    3,423
    1,819
    71
    I had plans to finish the subroadbed on the ‘high line’ on the upper level between Smithville and West Union and a few other items. However storms Thursday night caused a power outage which was restored Friday. Then we had another storm Saturday that caused a 27 hour power outage through most of Sunday.

    Despite losing two mornings to work on the layout, I was able to install some ceiling panels and glue down the first section of track on the upper level. I also installed three custom Bowser covered hopper kits from Three Notch Rail.
    [​IMG]

    [​IMG]

    The goal for this week is to get one section of flex track installed each evening before bedtime. That should lead to substantial progress going into next weekend.


    Sent from my iPhone using Tapatalk
     
    Joe Lovett, BNSF FAN and BoxcabE50 like this.
  8. GP30

    GP30 TrainBoard Member

    3,423
    1,819
    71
    STEEL IS (or will be) KING!

    After overlaying the plywood base last weekend with the foam sheeting, I laid out and glued the track down for the rolling mill for Kanawha Electra Steel on the peninsula near Charleston. Two ends from the Walthers kit were cut down to two stalls and propped up in place for the visual. Once the backdrop is completed behind, the structure will be assembled and set in place.
    [​IMG]


    We also completed the main track subroadbed between Smithville and West Union was installed and the roadbed installation began at Spencer. Some of the yard tracks at Spencer were also sketched out. I’ll have to get more foam sheet glued down before laying track here. This may also be a good time to go ahead and get the backdrop put in before getting too far ahead.
    [​IMG]


    Sent from my iPhone using Tapatalk
     